How long does it take to build a pool?

Building a swimming pool is an exciting endeavour that brings endless enjoyment to your home. But, how long does it take to build a pool? Understanding the different stages and factors involved in pool construction is crucial for managing expectations and ensuring a smooth process.
How long does it take to build a swimming pool?

Short Summary

  • The type of pool chosen, the planning process and obtaining permits & approvals all influence how long it takes to build a pool.
  • Concrete pools usually take 10-20 weeks to complete while fibreglass pools are typically a 3-8 week project.
  • Choosing the right builder and navigating local regulations are key for a successful project.

Factors affecting pool construction time

There are several factors that play a crucial role in determining the time it takes to build a swimming pool. The type of pool chosen, the planning process, and obtaining permits and approvals all contribute to the overall construction time of most pool projects. It's essential to consider these factors when embarking on a new pool project to ensure that you are well-prepared for the journey ahead.

Each type of pool has its own unique construction process, which affects the time it takes to complete the project.

Type of pool

The type of pool you choose has a significant impact on the construction time. Concrete pools, for example, can take 3 to 4 months, or more, to complete due to their detailed and complex shapes, as well as the time required for curing the concrete. On the other hand, fibreglass pools are much faster to install, taking only a few days to fill with water and a few weeks to fully install.

This difference in construction time is heavily influenced by the materials used and the installation process. While concrete pools require extensive excavation and preparation, fibreglass pools come with a pre-formed shell that is placed directly into the excavated area.

Planning process

The planning process for a new pool is a critical aspect that greatly affects the overall construction time. It involves making important decisions such as the pool's size, shape, and features. Depending on your preferences and the complexity of your pool's design, the planning stage can take days or even months.

It's essential to give yourself enough time during the planning stage to make the right decisions for your pool. After all, a pool is a permanent fixture in your home, and you want to feel satisfied with the end result. Rushing through the planning process may lead to regrets down the line, so it's better to take your time and ensure that your pool meets all your expectations.

Permits and approvals

Before construction can begin, you'll need to secure the necessary pool building permits and approvals from your local authorities. This process involves the review and signing of the contract, paying a deposit, and submitting your plans to a surveyor. The time it takes to obtain these permits can vary greatly, with processing times ranging from 2 to 8 weeks depending on demand.

It's important to factor in the time it takes to obtain these permits when planning your pool project, as any delays in obtaining approvals can push back your construction timeline. Being proactive and working closely with your pool builder can help minimise these delays and ensure that your pool construction stays on track.

Concrete pools: Understanding the process

Concrete pools offer a high level of customisation, allowing you to create a unique and personalised swimming pool. However, this customisation comes with a longer construction time compared to other pool types. A typical concrete pool takes between 3 and 5 months to complete, depending on the complexity of the project and external factors such as weather conditions.

The process of building a concrete pool involves several stages, including excavation and preparation, structural, and the completion of finishing details. Each of these stages plays a crucial role in the overall construction time, so it's essential to have a clear understanding of what goes into a concrete pool project to ensure a successful outcome.

Excavation and preparation

The first stage in building a concrete pool is the excavation and preparation of the site. This involves digging out the area to the desired depth and shape. The excavation process may take up to one week, or longer for challenging sites. The actual waiting time can vary depending on the priority of your project in the contractor's schedule.

It's important to be patient during this stage, as rushing the excavation and preparation process can lead to issues down the line. Ensuring that the site is properly prepared and the pool shell is correctly positioned will help prevent problems such as uneven settling or structural issues in the future.

Structural

Once the site is prepared, the structural work for the concrete pool begins. This involves the installation of rebar to reinforce the pool shell, followed by the concrete spray. While this stage of the process is relatively quick, taking no more than two weeks usually, it's essential to have a qualified structural engineer inspect the steel reinforcement to ensure the pool's integrity and safety.

For complex builds and out of ground pools, this step can also include formwork, piers and footings. All of which will add time to the build time. Your pool builder should give you time guides of each stage before the build starts.

Once applied, the concrete structure of the pool needs time to cure. This curing process is essential to ensure the pool is strong, structurally sounds and ready for the next steps. Curing typically takes 3-4 weeks depending on the weather.

Finishing touches

The final stage of concrete pool construction involves the application of finishing touches such as tiling, interior, and the installation of coping, decking, and other chosen options. These details not only enhance the aesthetic appeal of your pool, but also ensure its longevity and durability.

The plumbing and filtration may be installed in this stage, or earlier.

While it may be tempting to rush through this stage to start enjoying your pool as soon as possible, it's important to remember that the wait is worth it. Taking the time to ensure that every detail is completed to the highest standard will result in a beautiful and functional pool that you can enjoy for years to come.

And if you're looking for alternative options that require less waiting time, there are other innovative pool options available, such as fibreglass, above-ground pools and prefabricated pools. Though most people fins with an investment like a swimming pool, it is worth waiting and getting what you truly want.

Fibreglass pools: A faster alternative

Fibreglass pools are a popular choice for those looking for a faster pool installation process. These pools are known for their quick installation time, typically taking between one to three weeks to install. The speed of installation is due to the pre-fabricated pool shell that is placed directly into the excavated area, eliminating the need for extensive preparation work.

The process of installing a fibreglass pool involves several stages, including the installation of the pool shell, plumbing and electrical work, and landscaping and fencing. While each of these stages plays a crucial role in the overall construction time, the main advantage of fibreglass pools is their speedy installation process, allowing you to enjoy your new pool sooner than with other pool types.

Pool shell installation

The installation of the fibreglass pool shell is the first and most crucial stage of the process. It involves using a crane to lift the pool from the truck and position it in the designated spot. This process typically takes a few hours, depending on the size and complexity of the pool shell.

The pool shell will be backfilled after being put int place. This ensures that the pool shell is properly supported and prevents uneven settling or structural issues in the future.

Plumbing and electrical work

After the pool shell is installed, the plumbing and electrical work for the fibreglass pool begins. This involves installing the requisite pumps and filters. The filtration works typically takes one day to complete, depending on the complexity of the systems and the availability of the necessary professionals.

It's important to ensure that the plumbing and filtration systems are properly installed and functioning, as any issues with these systems can lead to problems with the pool's performance and safety. Working closely with your pool builder and ensuring that all inspections are completed in a timely manner can help minimise delays and ensure that your pool is ready to enjoy as soon as possible.

Landscaping and fencing

The final stage of the fibreglass pool installation process involves landscaping and fencing. While these elements may not directly affect the functionality of the pool, they play a crucial role in enhancing the overall aesthetic and safety of the pool area.

In Australia, pool fencing is required by law to prevent unauthorised access and ensure the safety of young children. The fencing must be at least 1.2 meters high. It's essential to work with a qualified tradie to ensure that your pool's fencing meets all local regulations and safety standards.

Seasonal considerations in Australia

In Australia, the demand for pool builds increases during the summer months, with many homeowners looking to enjoy the warm weather by taking a dip in their new pool. As a result, it's important to plan your pool construction project accordingly to ensure that you can enjoy a full summer season in your new pool.

To maximise your pool enjoyment, it's best to enquire about pool construction in June or July, or even earlier if possible. This will allow ample time for the planning, permits, and construction process, ensuring that your pool is ready to enjoy by the time the warm summer weather arrives.

By planning ahead and working closely with other sub-contractors and your pool builder, you can ensure that your pool project runs smoothly and you're able to make the most of the summer season.

Choosing the right pool builder

Selecting the right pool builder is essential to the success of your pool project. A reputable and experienced pool builder will be able to guide you through the entire process, from planning and design to construction and maintenance. Luckily, you're at the right place. Poolz has the largest selection of Australia's best pool builders and makes it easy to get three quotes.

Navigating local regulations

Before construction can begin on your pool project, you'll need to navigate local regulations and obtain the necessary permits and approvals. Local authorities must approve a development application before construction can begin, with processing times varying from 2 to 6 weeks depending on demand and complexity.

It's important to be aware of these regulations and work closely with your pool builder, who should handle all these requirements, to ensure that your pool project complies with all local requirements. By staying informed and proactive throughout the permit process, you can minimise delays and ensure that your pool build stays on track.

Conclusion

In conclusion, the time it takes to build a pool depends on various factors, such as the type of pool, planning process, and obtaining permits and approvals. By understanding these factors and working closely with a reputable pool builder, you can ensure that your pool construction project runs smoothly and results in a beautiful and functional swimming pool that you can enjoy for years to come. So dive into the planning process and start making your dream pool a reality!

Frequently asked questions

Can’t find what you’re looking for? Get in touch with our friendly team.
What warranties are provided when building a new pool?
Curved Arrow Icon

Swimming pool building warranties are provided, and the warranty depends on the state, pool type and company. For example, most concrete pools have a warranty equal to that of the State building licence requirements. So in Queensland, the warranty requirements for a concrete swimming pool are as determined by the QBCC and are usually 7 years. This varies slightly by State, but in most states is a similar period of time.

Fibreglass pools typically have a longer warrant that covers the structural integrity of the shell, in most cases 25 year or lifetime. That being said, these warranties have stringent requirements on the homeowner to record chemical tests on a regular basis and as such, are not as straight forward as they appear.

If you have any questions about warranties, please get in touch with us and we'll be happy to assist you.

How long does it take to get a prefabricated pool installed in Australia?
Curved Arrow Icon

On average, it takes 2-4 weeks to install and complete a prefabricated pool in Australia. The exact duration of time depends on the location the pool is placed (for example, a pool placed on 15m high poles in front of your house on the hillside will take considerably longer, whereas a pool placed on relatively flat ground in your backyard may be done even quicker) and the other elements around your pool such as decking, tiling, fencing and landscaping.

How long does it take to build a concrete pool in Australia?
Curved Arrow Icon

On average, it takes around 10 to 16 weeks to build a concrete swimming pool in Australia, from start to finish. The exact duration of time depends on factors such as the complexity of the project and weather conditions.

How long does it take to build a fibreglass pool in Australia?
Curved Arrow Icon

On average, it takes around 2 to 8 weeks to install and complete a fibreglass pool in Australia, from start to finish. The exact duration of time depends on the elements around your pool such as decking, tiling, fencing and landscaping, and of course, weather conditions.

The manufacturing time also needs to be considered.